The all-new Regent Cinema is set to open its doors in late 2022. The £9.6m venue, prepared by Merlin Cinemas is on the site of the former much-loved cinema which had to be demolished due to structural problems. Bam Construction led the construction of the new building including a large basement area underground, on Redcar seafront. HATCRETE Redcar Sand Adcolour was supplied by HATCRETE to Poundfield Precast who manufactured the concrete precast panels. The HATCRETE technical team visited the site to monitor production from the plant to the slabs being placed.
PROJECT REQUIREMENTS
To supply 254m³ of HATCRETE Redcar Sand Adcolour for the precast panel units surrounding the underground basement area and above.
PRODUCTS USED:
PARTICIPANTS: